Point of departure: Jiangxi,Nanchang/Jiangsu,Changzhou
Point of destination: Uzbekistan, Tashkent
Item name: transformer
Transportation time: since November, 2019
Project description:
The project of reconstruction of three cascade hydroelectric power stations of Uzbekistan, including Nizhne-Bozsuiskaya №14, Tashkentskaya №9, Shakhrikhanskaya №3 and others. In July started asking for prices, in August a Contract was signed, by October a deliver option was determined, November - the beginning of transportation. Despite the relatively big changes in the amounts at the intermediate stage, thanks to our professionality and coordination skills we were able to decide on the final transportation option. The item successfully delivered to destination place.